Padero delivers a “50kW Self-funded”system before the March FIT review

Image
This project was started with only 8 days to connect to the Western Power network. This 50kW system utilised Wurth aluminium mounting technology, along with 206 LDK panels. The owner of the building wanted to take advantage of the looming FIT review, whilst reducing his energy overhead and dependency on the grid. This project was connected on time and on budget. The owner is extremely pleased with the generation to date, with an expected £16,000 per annum being generated from this system, resulting in a return of initial investment in around 4.5 years.